Actions are taken by Government of Odisha for improvement of water quality of Gangua nallah

Construction of five STPs of total 184 MLD capacity based on Sequential batch Reactor Technology

photos of STPS

Sources  of  contamination   Action  Plan Implementing Dept. / Organization
Discharge of untreated domestic waste water Lean Flow of River Daya 1.Construction of 6 nos of STPs
Location of STP Capacity of STP
Meherpali 56 MLD
Basuaghai 28 MLD
Kochilaput 43.5 MLD
Paikarapur 8.5 MLD
Rokad 48 MLD
H & UD/ OWSSB Water Resources Dept

Improvement of Sewer network of Bhubaneswar City so as to divert the wastewater from drains to STPs being installed in respective sewerage districts instead of being discharged to Gangua nallah (Drain Map, Gangua, STP location)

Commissioning of Septage Treatment Plant (SeTP) of 75 KLD capacity to treat liquid part of the septage using DEWATS technology.

Proposal for construction of two more Septage Treatment Plants in Bhubaneswar city.

Sl. No. Location Population to be served Capacity Cost (Rs.in crore)
1 Gadakana (near MPS, Sewerage District-VI, Bhubaneswar) 1,50,000 75 KLD 4.00
2 Kochilaput (near STP, Sewerage District-III, Bhubaneswar) 1,50,000 75 KLD 4.00

Construction of community Toilets to prevent Open defecation.


Scope, location and scheduled completion date of STPs to be established in Bhubaneswar city

Scope, location and scheduled completion date of STPs to be established in Bhubaneswar city

<
Sewage Districts (SD)   Project Scope Name of Location of STP Scheduled Commencement Date Progress Scheduled Completion Date
SD- I  Sewer laying 76.146 Km Sewage Pumping Station – 5 Nos. STP Capacity -56 MLD- 1 No. Meherapalli 27.07.2017 Under Progress 26.07.2020
SD- II Sewer laying  27.728 Km Sewage Pumping Station – 5 Nos. STP Capacity -28 MLD- 1 No. Basuaghai 26.10.2017 Under Progress 25.10.2020
SD- III Sewer laying  97.812 Km Sewage Pumping Station – 9 Nos. STP Capacity -43.5 MLD- 1 No. Kochilaput 27.07.2017 Under Progress 26.07.2020
SD- IV  Sewer laying  14.24 Km Sewage Pumping Station – 3 Nos. STP Capacity -8.5 MLD- 1 No. Paikarapur 09.02.2018 Under Progress 08.02.2020
SD- VI   Sewer laying  254.58 Km Sewage Pumping Station – 9 Nos. STP Capacity -48 MLD- 1 No. Rokat 26.06.2013 Under Progress Sep, 2019